Facilities Management
Horn Lodge Residence
WIU Project Manager Andy Daniels
Project Scope New residence for Horn Field Lodge Director in new location
External Vendors Leander Construction, utilities by Facilities Management in-house crew and Cortelyou Excavating
Total Project Cost Approximately $100,000 (includes utilities)
Completion Date August 15, 2014
Project Description
Install new home in new location. Install new water, sewer, and electricity to the new home. Remove the existing home.
Updates
The residence is installed. Facilities Management is awaiting final grading, seeding, and hook up of the LP tank. The Director is living in the new residence at this time.