WIU Project Manager Ted N. Renner
Project Scope Complete removal and replacement of the lower bleachers and renovation of the north balcony bleachers in Western Hall.  
External Vendors Carroll Seating and Huffman Welding
Total Project Cost Approximately $900,000 
Completion Date August 5, 2016 

Project Description

The Western Hall bleacher replacement and rehabilitation project will consist of the complete removal and replacement of the lower bleachers and renovation of the north balcony bleachers in Western Hall. The renovation is currently necessary due to the fact the existing bleachers do not meet current ADA code; they are at the end of their service life; they are difficult to operate; and service parts are no longer being manufactured. Furthermore, in conjunction with this work, entrances into the gym that were covered in 1985 will be reopened in order to meet recent National Fire Protection Association egress requirements for large events. This work was unanimously approved by Student Government Association in September of 2015. When completed, the project will update life safety requirements of Western Hall while simultaneously increase seating capacity for any event held therein. 

Updates

Demolition on the current bleachers began on Monday, May 23, 2016.  The second floor seat installation will began the week of July 25. 

Photos

May 23, 2016 May 24, 2016 South bleachers 05_27_16 Upper north bleachers 05_27_16 north bleachers 05_27_16 North bleacher dissassembly south bleachers 06_01_16 North bleachers 06_01_16 _DSC6395 June 6, 2016 - North wall South wall Vomitory Vomitory Vomitory New bleachers - June 7, 2016 June 15, 2016 New seats June 24, 2016 July 5, 2016 Bleachers on the south side - July 7, 2016 bleacher side covers north balcony bleachers - July 26, 2016 Western Hall Bleachers Western Hall Bleachers Western Hall Bleachers Western Hall Bleachers Western Hall Bleachers Western Hall Bleachers Western Hall Handrails