Tanner Hall Lobby Remodel

WIU Project Manager Michael Hott
Project Scope Remodel of the Tanner Hall Lobby 
Total Project Cost Approximately $110,000 
Completion Date August 14, 2015

Project Description

Remove original aluminum and glass panel system at reception desk within lobby; install new plastic laminate on desk; install new flooring in lobby and both corridors flanking lobby and leading to elevator core; replace lighting in both corridors with L.E.E.D. compliant LED energy efficient fixtures; painting throughout aforementioned spaces to create updated, future leaning inviting environment to encourage, promote, and improve student recruitment and retention. All of this work is being done in-house with the exception of the flooring which will be done by Hollister Home Center. 

Updates

As of August 11, 2015, the project is 85% complete. The flooring is 90% complete. The painting and the flooring will be done by Friday, August 14. There still will be some necessary finish items that will be completed before August 21. 

Photos

Before Before Before Before Before During Construction - June 26, 2015 June 26, 2015 June 26, 2015 June 26, 2015 June 26, 2015 June 26, 2015 June 30, 2015 June 30, 2015 June 30, 2015 June 30, 2015 curved stainless steel panels to be attached to reception desk's face July 10, 2015 July 10, 2015 July 13, 2015 - Tanner Hall lobby painting July 15, 2015 July 15, 2015 August 11, 2015 Painting in Tanner Lobby Floor tile being installed Carpet behind the front desk Tanner elevator lobby Tanner Lobby Front Desk