WIU Project Manager Andy Daniels
Project Scope Repair to a section of the drive at North Quad
External Vendors Hood Demolition
Total Project Cost Approximately $23,000
Completion Date June 30, 2016
Description
A portion of the drive to North Quad will be repaired. Several portions of the drive are deteriorating and may present a hazard to vehicles.
Updates
As of July 5, 2016, the road is open for traffic. There is still some patching to be done and seeding will occur after Labor Day.